Active Standard

IEEE 1248-2020

IEEE Guide for the Commissioning of Electrical Systems in Hydroelectric Power Plants

Inspection procedures and tests for use following the completion of the installation of components and systems through to commercial operation are provided. This guide is directed to plant owners, designers, and contractors involved in the commissioning of electrical systems of hydroelectric plants.

Sponsor Committee
PE/EDPG - Energy Development & Power Generation
Learn More
Status
Active Standard
PAR Approval
2014-03-27
Superseding
1248-1998
Board Approval
2020-03-05
History
Published:
2020-05-05

Working Group Details

Society
IEEE Power and Energy Society
Learn More
Sponsor Committee
PE/EDPG - Energy Development & Power Generation
Learn More
Working Group
HPS - WG 1248 - HPS - Commissioning of Electrical Systems in Hydroelectric Power Plants Working Group
Learn More
IEEE Program Manager
Malia Zaman
Contact
Working Group Chair
John Yale
No Active Projects
No Active Standards

1248-1998

IEEE Guide for the Commissioning of Electrical Systems in Hydroelectric Power Plants

Inspection procedures and tests for use following the completion of the installation of components and systems through to commercial operation are provided. This guide is directed to the plant owners, designers, and contractors involved in the commissioning of electrical systems of hydroelectric plants.

Learn More

No Inactive-Withdrawn Standards
No Inactive-Reserved Standards
Newswire

Sign up for our monthly newsletter to learn about new developments, including resources, insights and more.