The type, production, commissioning, and periodic tests, and evaluations that shall be performed to confirm that the interconnection and interoperation functions of equipment and systems interconnecting distributed energy resources with the electric power system conform to IEEE Std 1547 are specified in this standard.
- Standard Committee
- BOG/SC21 - Distributed Generation, Energy Storage and Interoperability Standards Committee
- Status
- Active Standard
- PAR Approval
- 2014-12-10
- Superseding
- 1547.1-2005
- Proposed Amendment
-
P1547.1a
- Board Approval
- 2020-03-05
- History
-
- Published:
- 2020-05-21
Additional Resources
- Downloads
- 1547.1-2020_downloads.zip
Working Group Details
- Society
- Standard Committee
- BOG/SC21 - Distributed Generation, Energy Storage and Interoperability Standards Committee
- Working Group
-
1547.1 testing WG - 1547.1 testing WG for interconnecting DR with EPS's
- IEEE Program Manager
- Malia Zaman
Contact Malia Zaman - Working Group Chair
- Timothy Zgonena
Other Activities From This Working Group
Current projects that have been authorized by the IEEE SA Standards Board to develop a standard.
P1547.1a
Standard Conformance Test Procedures for Equipment Interconnecting Distributed Energy Resources with Electric Power Systems and Associated Interfaces Amendment 1
This standard integrates clarifications and corrections identified in the extensive additions to UL 1741 3rd Ed. Supplement SB that incorporated test procedures in IEEE 1547.1-2020.
Standards approved by the IEEE SA Standards Board that are within the 10-year lifecycle.
No Active Standards
These standards have been replaced with a revised version of the standard, or by a compilation of the original active standard and all its existing amendments, corrigenda, and errata.
1547.1a-2015
IEEE Standard Conformance Test Procedures for Equipment Interconnecting Distributed Resources with Electric Power Systems - Amendment 1
This amendment was prepared in response to IEEE Std 1547a(TM), Amendment 1 to IEEE Std 1547(TM)-2003 providing revisions to Clause 4.1.1 Voltage regulation, Clause 4.2.4 Frequency, and Clause 4.2.3 Voltage.
These standards have been removed from active status through a ballot where the standard is made inactive as a consensus decision of a balloting group.
No Inactive-Withdrawn Standards
These standards are removed from active status through an administrative process for standards that have not undergone a revision process within 10 years.
No Inactive-Reserved Standards