Guide for Development of Specifications for Turnkey Substation Projects

The scope of this guide is to provide methodologies and practices for a systematic and coordinated approach for the development of requirements and specifications for turnkey substation projects.

Standard Committee
PE/SUB - Substations Committee
Status
Active PAR
PAR Approval
2020-02-13
Superseding
1267-2019

Working Group Details

Society
IEEE Power and Energy Society
Standard Committee
PE/SUB - Substations Committee
Working Group
WGD8 - WGD8 - Specification for Turnkey Substation Projects
IEEE Program Manager
Patricia Roder
Contact Patricia Roder
Working Group Chair
Michael Nadeau

Other Activities From This Working Group

Current projects that have been authorized by the IEEE SA Standards Board to develop a standard.


No Active Projects

Standards approved by the IEEE SA Standards Board that are within the 10-year lifecycle.


1267-2019
IEEE Guide for Development of Specifications for Turnkey Substation Projects

Systematic methodology, guidelines and practices for developing turnkey substation specifications are provided in this guide. Guidance on engineering, procurement, construction, testing and commissioning, quality assurance/quality control and training is provided.

Learn More About 1267-2019

These standards have been replaced with a revised version of the standard, or by a compilation of the original active standard and all its existing amendments, corrigenda, and errata.


No Superseded Standards

These standards have been removed from active status through a ballot where the standard is made inactive as a consensus decision of a balloting group.


No Inactive-Withdrawn Standards

These standards are removed from active status through an administrative process for standards that have not undergone a revision process within 10 years.


No Inactive-Reserved Standards
Subscribe to our Newsletter

Sign up for our monthly newsletter to learn about new developments, including resources, insights and more.